Subject: fw : e - next spreadsheet
here are the current items and projected disbursements in e - next for plant development .
1 . ft pierce hrsg is an option payment . once the option is exercised , i believe the remaining payments would be made over the following 12 month period .
2 . longview turbines : we continue to make progress payments . i believe the payments will be completed over the following 12 months as well .
3 . cascade agreement / transformer : awaiting notice to proceed . cascade will be paid over 4 months . transformer over 1 year .
- - - - - original message - - - - -
from : clark , catherine
sent : monday , november 05 , 2001 10 : 42 am
to : deffner , joseph
subject : e - next spreadsheet