Subject: re : westinghouse 501 d 5 a
louise :
our proposal is for ena to assume the nominal cost of the turbine as of jan 1 , ' 01 , exclusive of carrying costs up to that date . from jan 1 forward we will assume full responsibility for any carrying costs , and any continuing payment obligations under the purchase contract with westinghouse .
the nominal cost of the turbine as of jan 1 , ' 01 exclusive of carrying costs , is $ 22 , 947 , 599 . this is the amount that we propose ena to assume with respect to the turbine .
the carrying cost through jan 1 to be assumed by calme as part of this proposal is $ 2 , 055 , 330 . this amount reflects the actual carrying charges imposed by enron corp on calme based upon the payments made to westinghouse under the purchase agreement .
the continuing payment obligation to be assumed by ena under the purchase contract with westinghouse is $ 1 , 558 , 401 . this amount reflects the actual final payment due under the contract , which is due at commercial operations .
please let me know if you need anything else to resolve this , or if you have any questions .
regards ,
ben
louise kitchen
03 / 26 / 2001 12 : 45 pm
to : ben jacoby / hou / ect @ ect
cc :
subject : re : europe ' s turbines
can you send me a quick email summary of what we want the calme trasfer to be and i ' ll deal with it .
thanks
louise
enron capital & trade resources corp . from : ben f jacoby 03 / 26 / 2001 12 : 42 pm
sent by : ben jacoby
to : louise kitchen / hou / ect @ ect
cc :
subject : re : europe ' s turbines
ok .
by the way , did you have a discussion with calme on the carrying costs on the westinghouse 501 d 5 a ?
regards ,
ben
louise kitchen
03 / 26 / 2001 10 : 17 am
to : ben jacoby / hou / ect @ ect
cc :
subject : europe ' s turbines
eel is now selling its 9 fas ( previously mentioned for arcos ) , i referred john sherriff to you to see if you have any potential outlets for these turbines . so in case someone telephones you , that is where the call comes from .
louise